A company subcontracted to build five police stations on Thursday filed a petition with the Department of Special Investigation (DSI) against PCC Development and Construction Co (PCC), accusing it of fraud.

The petition was filed on behalf of S.L. Development and Construction Co by Kornpat Paiboonsirikul, a construction engineer, with Pol Lt-Col Thawal Mangkhang, the DSI's special cases specialist.

Mr Kornpat said S.L. Development and Construction was subcontracted by PCC on July 8, 2011 to build one large police station and four small ones. The median price set for the large station was 19.2  million baht and for the small ones between 5.5 million and 5.8 million baht.

This article is older than 60 days, which we reserve for our premium members only.You can subscribe to our premium member subscription, here.

Your comments

  • Discussion 14 : 08 Feb 2013 at 22.3014

    Did that subcontractor make a bid without knowing the specifications ?!

  • Discussion 13 : 08 Feb 2013 at 08.1713

    my wife says that PCC is Newin Chidchob's father's construction company in Chiang Mai

  • Discussion 12 : 08 Feb 2013 at 06.0812

    BP do an investigation....never!

  • Discussion 11 : 08 Feb 2013 at 00.3011

    @jwatch, d9.

    I agree. If the subcontractor wins the case, it could really change the way thai business works. And I think thai companies can permanently forget to do any business with foreign companies, at least if done under thai law.

    I plan to sue my boss tomorrow. My contract for the last several years says x baht, but I realise now I should have had twice that all along!

  • Discussion 10 : 07 Feb 2013 at 22.3410

    .

    Who is PCC ?

    Who support PCC ?

    Perhaps BP could please do some investigation !


    .

  • Discussion 9 : 07 Feb 2013 at 21.349

    I didn't know I could sue if I made less money than I expected ..this is a great news!

  • Discussion 8 : 07 Feb 2013 at 20.588

    .

    Contractor to Sub-contractor...

    Why the " Thorough Study of the plan " was done after the sub-contractor was made and accepted.

    Who is BS who ?


    .

  • Discussion 7 : 07 Feb 2013 at 20.467

    Two guesses where the money has gone.When will Thai people realise there so called leaders are bleeding them dry.Sorry to say it but you get what you deserve if you continue to be so nieve.

  • Discussion 6 : 07 Feb 2013 at 20.426

    Two guesses where the money is

  • Discussion 5 : 07 Feb 2013 at 19.545

    'But from thorough examination of the blueprints by engineers, the company found that the large station would cost 26 million baht, not 19.2 million baht,'Mr Kornpat said S.L. Development and Construction was subcontracted by PCC on July 8, 2011.'

    His company just examine the blueprints now?

Reply

Sign in once and access every part of the website at your convenience!

Please log in to our Bangkokpost.com community to post your comment.
You can sign in to the community by clicking here.

If you are not part of the community yet, please sign up here. By being part of this community you will get all these privileges.